Tomorrow World Real Estate Development L.L.C
Registered with DLD: 13 Jun 2024
Projects
4n = 4i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 4
Last refreshed: 23 Nov 2026
Completed
0n = 4i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 4
Last refreshed: 23 Nov 2026
Active / pending
4Average completion (active): 18%n = 4i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 4
Last refreshed: 23 Nov 2026
Past planned date
1n = 4i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 4
Last refreshed: 23 Nov 2026
Projects past their planned completion date
Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| Tomorrow Commercial Tower | Active | 70% | 31 Jul 2026 |
All registered projects
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| THE BAY interiors by MISSONI | Not started | 0% | 30 Sept 2029 |
| Tomorrow Commercial Tower 2 | Not started | 0% | 30 Jun 2029 |
| Tomorrow 166 | Active | 2% | 31 May 2027 |
| Tomorrow Commercial Tower | Active | 70% | 31 Jul 2026 |