Tabeer Real Estate Development L.L.C
Registered with DLD: 25 Feb 2015
Projects
6n = 6i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 6
Last refreshed: 23 Nov 2026
Completed
3n = 6i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 6
Last refreshed: 23 Nov 2026
Active / pending
3Average completion (active): 47%n = 6i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 6
Last refreshed: 23 Nov 2026
Past planned date
1n = 6i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 6
Last refreshed: 23 Nov 2026
Projects past their planned completion date
Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| 99 Park Place | Active | 90% | 31 Dec 2025 |
All registered projects
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| 368 Park Ln | Not started | 0% | 31 Aug 2028 |
| Parkside Boulevard | Active | 52% | 27 Dec 2027 |
| 99 Park Place | Active | 90% | 31 Dec 2025 |
| 48 Parkside | Completed | 100% | 30 Sept 2025 |
| Tabeer 1 | Completed | 100% | 15 Jun 2022 |
| Dragon View | Completed | 100% | 31 Aug 2016 |