Pantheon Elysee Real Estate Development L.L.C
Registered with DLD: 25 Aug 2021
Projects
7n = 7i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 7
Last refreshed: 23 Nov 2026
Completed
1n = 7i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 7
Last refreshed: 23 Nov 2026
Active / pending
6Average completion (active): 22%n = 7i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 7
Last refreshed: 23 Nov 2026
Past planned date
1n = 7i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 7
Last refreshed: 23 Nov 2026
Projects past their planned completion date
Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| Elysee Heights | Active | 81% | 14 Apr 2026 |
All registered projects
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| Maison Elysee II | Active | 23% | – |
| Voxa Residences | Active | 4% | 31 Dec 2028 |
| Omya Residences | Not started | 0% | 30 Jun 2028 |
| Maison Elysee III By Pantheon | Active | 4% | 31 Oct 2027 |
| Maison Elysee I | Active | 21% | 31 Mar 2027 |
| Elysee Heights | Active | 81% | 14 Apr 2026 |
| Elysee III by Pantheon | Completed | 100% | 30 Sept 2024 |