Know Dubai PropertyFrom official DLD records

Majid Developments L.L.C

Registered with DLD: 6 Jul 2023

Projects
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 4

Last refreshed: 22 Nov 2026

4n = 4
Completed
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 4

Last refreshed: 22 Nov 2026

0n = 4
Active / pending
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 4

Last refreshed: 22 Nov 2026

4Average completion (active): 19%n = 4
Past planned date
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 4

Last refreshed: 22 Nov 2026

1n = 4

Projects past their planned completion date

Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.

ProjectsProject statusCompletionPlanned completion
Mayfair Gardens By MajidActive70%14 Aug 2026

All registered projects

ProjectsProject statusCompletionPlanned completion
جورا تيراسيز من مجيدPending0%30 Jun 2029
Arlington Park II By MajidNot started0%1 Apr 2028
ARLINGTON PARK By MAJIDActive6%31 Dec 2027
Mayfair Gardens By MajidActive70%14 Aug 2026