Majid Al Futtaim Tilal Al Ghaf Phase A L.L.C

Registered with DLD: 11 Feb 2018

Projects
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 9

Last refreshed: 23 Nov 2026

9n = 9
Completed
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 9

Last refreshed: 23 Nov 2026

3n = 9
Active / pending
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 9

Last refreshed: 23 Nov 2026

6Average completion (active): 68%n = 9
Past planned date
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 9

Last refreshed: 23 Nov 2026

3n = 9

Projects past their planned completion date

Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.

ProjectsProject statusCompletionPlanned completion
LANAI IslandActive61%30 Sept 2026
AlayaActive91%20 Jul 2026
Elysian MansionsActive95%31 Mar 2025

All registered projects

ProjectsProject statusCompletionPlanned completion
AmaraActive71%–
Plagette 32Active61%–
Serenity MansionsActive32%–
LANAI IslandActive61%30 Sept 2026
AlayaActive91%20 Jul 2026
Elysian MansionsActive95%31 Mar 2025
AuraCompleted100%31 Aug 2024
HarmonyCompleted100%30 Jun 2024
ElanCompleted100%3 Nov 2023