Green Point Home Real Estate Development L.L.C

Registered with DLD: 2 Apr 2024

Projects
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 3

Last refreshed: 23 Nov 2026

3n = 3
Completed
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 3

Last refreshed: 23 Nov 2026

0n = 3
Active / pending
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 3

Last refreshed: 23 Nov 2026

3Average completion (active): 30%n = 3
Past planned date
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 3

Last refreshed: 23 Nov 2026

3n = 3

Projects past their planned completion date

Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.

ProjectsProject statusCompletionPlanned completion
ايكو هارموني تاورPending13%1 Oct 2026
ايكو فيوجن تاورPending37%15 Oct 2025
جرين سيل ريزيدنسزPending41%25 Jul 2025

All registered projects

ProjectsProject statusCompletionPlanned completion
ايكو هارموني تاورPending13%1 Oct 2026
ايكو فيوجن تاورPending37%15 Oct 2025
جرين سيل ريزيدنسزPending41%25 Jul 2025