Golden Wood Real Estate Development L.L.C
Registered with DLD: 18 Jun 2017
Projects
4n = 4i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 4
Last refreshed: 23 Nov 2026
Completed
2n = 4i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 4
Last refreshed: 23 Nov 2026
Active / pending
2Average completion (active): 90%n = 4i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 4
Last refreshed: 23 Nov 2026
Past planned date
2n = 4i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 4
Last refreshed: 23 Nov 2026
Projects past their planned completion date
Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| Golden Wood Views 5 | Active | 89% | 14 Oct 2026 |
| Views VII by Golden Woods | Active | 90% | 30 Jul 2026 |
All registered projects
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| Golden Wood Views 5 | Active | 89% | 14 Oct 2026 |
| Views VII by Golden Woods | Active | 90% | 30 Jul 2026 |
| Golden Wood Views -1 | Completed | 100% | 13 Sept 2022 |
| Golden Wood Views | Completed | 100% | 11 Jun 2020 |