Arada Developments L.L.C S.O.C

Registered with DLD: 1 Mar 2022

Projects
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 5

Last refreshed: 23 Nov 2026

5n = 5
Completed
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 5

Last refreshed: 23 Nov 2026

0n = 5
Active / pending
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 5

Last refreshed: 23 Nov 2026

5Average completion (active): 19%n = 5
Past planned date
i

Where this number comes from

Dataset: DLD projects register

Period: no records in this period

Sample size: 5

Last refreshed: 23 Nov 2026

1n = 5

Projects past their planned completion date

Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.

ProjectsProject statusCompletionPlanned completion
Jouri HillsActive78%30 Jun 2026

All registered projects

ProjectsProject statusCompletionPlanned completion
Inaura Hotels & ResidencesActive1%14 Jun 2030
Akala Hotels and ResidencesActive2%31 Oct 2029
W Residences at Dubai HarbourActive4%31 Dec 2028
Armani Beach Residences At Palm JumeirahActive10%31 Dec 2027
Jouri HillsActive78%30 Jun 2026