Al Qudra Estates L.L.C
Registered with DLD: 3 Mar 2019
Projects
3n = 3i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 3
Last refreshed: 23 Nov 2026
Completed
2n = 3i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 3
Last refreshed: 23 Nov 2026
Active / pending
1Average completion (active): 97%n = 3i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 3
Last refreshed: 23 Nov 2026
Past planned date
1n = 3i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 3
Last refreshed: 23 Nov 2026
Projects past their planned completion date
Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| Nad Al Sheba Gardens Phase 3 | Active | 97% | 19 Apr 2026 |
All registered projects
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| Nad Al Sheba Gardens Phase 3 | Active | 97% | 19 Apr 2026 |
| Nad Al Sheba Gardens Phase 2 | Completed | 100% | 1 Dec 2024 |
| Cherrywoods | Completed | 100% | 31 May 2022 |