Al Mazaya Holding Company
Registered with DLD: 29 May 2008
Projects
9n = 9i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 9
Last refreshed: 23 Nov 2026
Completed
8n = 9i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 9
Last refreshed: 23 Nov 2026
Active / pending
1Average completion (active): 55%n = 9i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 9
Last refreshed: 23 Nov 2026
Past planned date
1n = 9i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 9
Last refreshed: 23 Nov 2026
Projects past their planned completion date
Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| The Villa | Active | 55% | 11 Sept 2013 |
All registered projects
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| Qpoint Liwan-Plot R016 | Completed | 100% | 15 Jan 2017 |
| Qpoint Liwan-Plot R017 | Completed | 100% | 10 Jan 2017 |
| Qpoint Liwan-Plot R009 | Completed | 100% | 28 Nov 2016 |
| Qpoint Liwan-Plot R096 | Completed | 100% | 6 Aug 2015 |
| Qpoint Liwan-Plotr001 | Completed | 100% | 19 Jan 2014 |
| The Villa | Active | 55% | 11 Sept 2013 |
| Business Avenue Aa1 | Completed | 100% | 22 Mar 2011 |
| Business Avenue Bb1 | Completed | 100% | 17 Jan 2011 |
| Business Avenue Bb2 | Completed | 100% | 28 Nov 2010 |