Ahmadyar Real Estate Development L.L.C
Registered with DLD: 20 Nov 2023
Projects
3n = 3i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 3
Last refreshed: 23 Nov 2026
Completed
0n = 3i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 3
Last refreshed: 23 Nov 2026
Active / pending
3Average completion (active): 30%n = 3i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 3
Last refreshed: 23 Nov 2026
Past planned date
1n = 3i
Where this number comes from
Dataset: DLD projects register
Period: no records in this period
Sample size: 3
Last refreshed: 23 Nov 2026
Projects past their planned completion date
Active projects whose planned completion date has passed while completion is below 100%. Dates can be extended officially; this is a factual comparison, not a judgement.
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| Palatium Residences | Active | 88% | 31 Mar 2026 |
All registered projects
| Projects | Project status | Completion | Planned completion |
|---|---|---|---|
| لافيرا كريك باي احمديار | Pending | 0% | 30 Sept 2029 |
| Vestoria Bay | Active | 4% | 25 Nov 2027 |
| Palatium Residences | Active | 88% | 31 Mar 2026 |